The Effect of Lot Size on Productivity
The more parts to be produced, the more elaborate the manufacturing process. Here are some other important considerations that can impact productivity.
Share
Understanding factors that contribute to your company’s identity, and addressing those that are most important to your company, will dramatically improve its CNC machine utilization. In past months, I have discussed company type, repeat business and lead time. This month, I am focusing on lot size, which I define as the number of workpieces produced during a single production run.
Almost every process-related decision you make should begin with a simple question: “How many parts are we making?” The more parts to be produced, the more elaborate your processes can be. There will, however, be challenges throughout the entire lot-size spectrum. For this discussion, I define lot sizes as:
- Extremely small (1-3 parts)
- Small (3-20 parts)
- Medium (21-100 parts)
- Large (100-1,000 parts)
- Extremely large (more than 1,000 parts)
Process Considerations
With smaller lot sizes and assuming program execution time is relatively short, no special consideration need be given to workholding or cutting tool selection. Just about any process that makes an acceptable workpiece will work. But as lot sizes grow, so does the need to reduce program-execution time while maintaining quality specifications. Any additional costs incurred because of a more elaborate process will be justified by the reduced time needed to complete the production run. With extremely large lot sizes, you should be able to justify anything it takes to get the last second out of the machining cycle.
Programming Considerations
With extremely small through small lot sizes, and especially when combined with short cycle times and few repeated jobs, offline programmers will not be able to keep up with production needs. If programming time is not internal to production run time, you should consider shopfloor-programmed (conversational) CNCs and having your CNC operators create programs during setup.
Engineering Considerations
The engineering I am thinking of here is related to making things easier for the setup person and operator: documentation and the like. The goal is to minimize mistakes and save time. With smaller lot sizes, and especially with limited repeat business, it may be difficult to justify much engineering past developing a machining process and creating rudimentary setup instructions. With minimal engineering, of course, the operator running the job must be highly skilled. (An exception is if you know the job will be repeated multiple times in the future, since the engineering time and effort can be justified over the part’s life.)
As lot sizes grow, it is likely that more than one person will be involved with the production run (tool-crib attendants; setup people; first, second and third shifts; inspectors; and so on). In these cases, there is a much greater need for task-simplifying engineering. Additional documents could include more elaborate setup instructions that list components and their locations, process drawings that specify machining operations to be performed and control sheets that describe measurements to be taken along with the offsets needing adjustment. In addition to documentation, task-simplifying engineering can include any studies and actions that improve the way a job is run.
Setup and Cycle-Time Reduction Considerations
I define setup time as the period from running the last part in the previous production run to running the first (good) workpiece in the next production run. Cycle time (per part) is the total time it takes to run the rest of the parts divided by how many parts have been run.
Given similar program execution times, machines will be in setup for a greater percentage of production run time when running smaller lots. With very small lot sizes, for instance, it is not uncommon for setup time to far exceed the time required to run out the job. When trying to improve machine utilization given this scenario, you should first concentrate on setup time.
As lot sizes grow, the percentage of time a machine is in setup will shrink. With large and very large lots, setup may be but a small part of the production run. In these cases, it would be better to target cycle time for improvement. While you should concentrate on things that happen during every cycle, like program execution time, part load/unload, cleaning/deburring and so on, don’t forget about things that do not, like tool maintenance, sampling inspections and machine warmup.
Personnel Utilization Considerations
The larger the average lot size, the more tasks that can be performed offline in preparation for upcoming jobs. As lot sizes grow, there comes what I call a break-even point when there is ample time for someone (probably not the setup person or operator) to do all of legwork needed for upcoming jobs. Setup-related tasks could include acquiring related documentation, gathering components and measuring devices, assembling cutting tools, and taking certain cutting tool measurements. Production-run tasks could include gathering resources to complete the run, like inserts, raw material and coolant. This will minimize the amount of work a setup person or operator must do while the machine is down.
Related Content
Tips for Designing CNC Programs That Help Operators
The way a G-code program is formatted directly affects the productivity of the CNC people who use them. Design CNC programs that make CNC setup people and operators’ jobs easier.
Read More6 Ways to Streamline the Setup Process
The primary goal of a setup reduction program must be to keep setup people working at the machine during the entire setup process.
Read MoreTroubleshooting Differences in Programming Methods, Machine Usage
Regardless of the level of consistency among machines owned by your company, you probably have experienced consistency-related issues. Here are some tips to help solve them.
Read More2 Secondary Coordinate Systems You Should Know
Coordinate systems tell a CNC machine where to position the cutting tool during the program’s execution for any purpose that requires the cutting tool to move.
Read MoreRead Next
Building Out a Foundation for Student Machinists
Autodesk and Haas have teamed up to produce an introductory course for students that covers the basics of CAD, CAM and CNC while providing them with a portfolio part.
Read More5 Rules of Thumb for Buying CNC Machine Tools
Use these tips to carefully plan your machine tool purchases and to avoid regretting your decision later.
Read MoreSetting Up the Building Blocks for a Digital Factory
Woodward Inc. spent over a year developing an API to connect machines to its digital factory. Caron Engineering’s MiConnect has cut most of this process while also granting the shop greater access to machine information.
Read More